Construction of the Ipswich Tidal Barrier

Main Contractor: VBA, a VolkerStevin, Boskalis Westminster and Atkins joint venture

Ipswich’s position on the estuary of the River Orwell in Suffolk makes it susceptible to fluvial and tidal flooding. The Ipswich Tidal Barrier Project is the final element of a £58 million programme of work by the Environmental Agency to upgrade the flood defences on the East and West bank and the Port of Ipswich itself. Due to the barrier permanently affecting the right of navigation through the new cut of the River Orwell, the Tidal Barrier works have required approval by the Secretary of State for the Environment Food and Rural Affairs, via a parliamentary order under the Transport and Work Act. The Ipswich Tidal Barrier order was made in August 2012.

Working with design and build contractor VBA, a VolkerStevin, Boskalis Westminster and Atkins joint venture, the Ipswich Tidal Barrier temporary works is the most advanced design delivered by MGF’s in-house design engineers.

Steve Hesketh, MGF’s Engineering Director said,

“Our design team enjoy taking on extremely complex projects and this was certainly one of our most challenging to date. Only by working closely with the permanent works design team and the contractor were we able to develop a practical and cost effective solution to an extremely complicated problem. Key to delivery was our detailed design and bespoke manufacturing agility, allowing the solution to evolve in response to the many site issues encountered.”

The contract was won based on a complete temporary works solution that delivered on cost, time, safety, quality, service and sustainability.

ipswich 5 1024x338 Case Study: Ipswich Tidal Barrier

One of the key differentiators in MGF’s service offering is the capability to manufacture bespoke components. 158 tonnes of fabricated steel was installed between the east and west banks of the Port. The 30m x 30m excavation allows safe working space to construct the colossal Tidal Barrier. Bespoke sections required just two weeks to fabricate and deliver direct to site from MGF’s Wigan workshop – one of eleven depots in the UK.

Stephen Barker, Major Project Engineer, explains more on the cofferdam design,

“This is a high risk and complex project due to the high loads imposed by the river and the variation in tidal conditions resulting in significant imbalances on each side of the wall. We twinned our modular 406UC brace however we manufactured 15m lengths to suit construction requirements and modified the joints to increase their capacity.

The imbalanced loads caused an issue with the frames pulling apart so we designed a 28m long 762×25.4 circular hollow section to tie the north and south waling beams together. The rest of the support consisted of 762×25.4 circular hollow section as knee braces, with four at 15.60m Long and four at 6.00m Long”

ipswich 4 Case Study: Ipswich Tidal Barrier

84 (No.) crimped pairs of AZ46-700N sheet piles formed the walls of the cofferdam extending 20.6m into predominately loose weathered chalk. In addition to the cofferdam – two sections of deflector piles – sheet piled walls have been installed to assist in diverting the river flows and reduce the loading on the temporary cofferdam.

Stephen Barker describes the next stage of works to allow construction of the gate,

“The second phase required eight raking props to be installed to the north and south walls, 4 on each, which allowed the bracing to the east and west walls to be removed following the first wall pours.

This change allows unimpeded construction of the barrier gate, but also has a key role to play as the raking props tie the sheet piles to the base slab to prevent the walls from being forced outwards into the river once the cofferdam is flooded during gate testing.”

The flagship cofferdam design is allowing the safe environment for around 40 employees working on this project daily. The gate itself is a hollow steel structure with radial arms pivoting at each end, designed by IRS, a German specialist firm, and was manufactured in the Netherlands by Hollandia. It will be floated across the North Sea in October 2017, fully assembled, and placed into the concrete civils structure across the River Orwell. The gate will operate in a similar way to the Thames Barrier and will rise during periods of extreme high tides to hold back the North Sea protecting 2,000 homes and businesses from the devastating effects of floods.


01 NATM MAGAZINE November 3 729x1024 Case Study: Ipswich Tidal Barrier

 

 

 

 

 

Printed in NATM Magazine, Nov 2017. View online

Download the PDF copy

 