Rising Main Replacement with GRiPSHORE at Wigton Road, Leeds

Rising Main Replacement with GRiPSHORE at Wigton Road, Leeds

Project: A project to replace a section of existing cast iron rising main in Leeds ‘Millionaire’s Row’ has called for MGF’s latest lightweight technology.

Customer: In Depth Civil Engineering and Barhale

As part of the Yorkshire Water AMP 6 programme, the MGF Yorkshire Depot supported Barhale to safely undertake the replacement of 930m of an existing rising main along Wigton Lane in Leeds, using the innovative safety solution GRiPSHORETM

GRiPSHORETM is MGF’s new lightweight shoring range which combines GRP (Glass Reinforced Plastic) materials with Trench Jacking Theory.

Working with the engineering department at Salford University, MGF’s research and development engineers combined light, flexible GRP materials with Trench Jacking theory to divert the loads from the soil onto the jacks and create a safe working environment quickly.

GRiPSHORETM is lightweight enough to transport in a van and very quick to assemble when reactive maintenance is needed for utilities works.

The size and value of the properties along Wigton Lane have earned it the nickname ‘Millionaires Row’ and as the existing main has deteriorated bursts and emergency repairs have caused widespread disruption including road closures and diversions.

The installation of the new main will solve this problem.

The existing main currently pumps waste water from Alwoodley pumping station to the local waste water treatment works along Wigton Lane.

The team are laying the new sewer on the opposite side of the carriageway to the existing sewer – so that the existing sewer can stay in use during the works.

The final part of the scheme will involve shutting down Alwoodley pumping station and diverting flows into the newly laid rising main.

MGF Technical Sales Representative Phil Ash was involved early in the scheme and advised on the use of the innovation GRiPSHORETM.

said Phil “At any one time approximately 100m of trench needed to be excavated by sub-contractor Indepth CE in preparation for a specialist pipe welding company to visit site to weld the pump main together at ground level then feed into the open trench. The GRiPSHORETM vertishore provided a fast, flexible & safe method of supporting the trench during this cycle of work”.

IMG 7950 640x427 300x200 Rising Main Replacement with GRiPSHORE at Wigton Road, Leeds

Wigton Lane

Chris Binks from Barhale added: “One of the best practices on the scheme is the use of GRiPSHORETM Vertishores supplied by MGF.

“Vertishores provide a lightweight, innovative way of safely supporting excavations within certain types of ground, up to certain depths.

“Due to the nature of the ground beneath Wigton Lane, the team have been able to utilise this product as a great way of advancing the operation quickly, whilst providing the same levels of safety as the traditional sheet and frame methods.”

The project started in July 2016 and is due to completed by the end of January 2017.

facebook Rising Main Replacement with GRiPSHORE at Wigton Road, Leedstwitter Rising Main Replacement with GRiPSHORE at Wigton Road, Leedsgoogle plus Rising Main Replacement with GRiPSHORE at Wigton Road, Leedspinterest Rising Main Replacement with GRiPSHORE at Wigton Road, Leedsemail Rising Main Replacement with GRiPSHORE at Wigton Road, Leeds